Prefabricated power modules

Prefabrication and modular build-out in blocks of 10–250 MW

A growing number of suppliers offer power and cooling systems that are built in factories and delivered in standardized blocks. This is close to how our concepts are structured, and we are investigating how the modules can be used in Swedish projects.

What the development involves

Vertiv OneCore is a prefabricated solution in which power and cooling are delivered as modules while the building is erected in parallel (Vertiv). Delta and Schneider Electric offer similar modular solutions (Delta, October 2026).

What benefits are documented

Suppliers cite shorter schedules, but we have not found any independent figures. The benefit depends on how well the modules fit the site and the building.

What it could mean in Sweden

With a modular build-out, a data center can be expanded as customers arrive and the grid connection grows. This suits projects of 10–25 MW and makes it easier to scale toward 100 MW and beyond.

What we are investigating

How the modules fit our concepts and Swedish building regulations. How transport, supplier dependency and interfaces with the building are managed. How procurement is structured so that several suppliers can compete.

Site, heat or capacity

Want to know more?

Tell us what you are working on, and we will tell you how the technology can be applied in a Swedish project.